Connection of biomethane producers
Biomethane that meets the specified quality requirements can be injected into the gas transmission system. Amber Grid, the Lithuanian gas transmission system operator (hereinafter referred to as the “TSO”), shall consult on all issues related to the connection of biogas production facilities to the gas transmission system, including:
- submission of applications,
- conditions for connection,
- connection agreements,
- connection design,
- carrying out of contract works.
Below is provided some basic information that is useful to know when preparing to connect biogas production facilities to the gas transmission system (click on the plus sign for more detailed information relevant to the specific step).
1. The Customer shall choose the place for the connection and decide on the desired capacity
Here you will find guidance on preparation for connection to the gas transmission system:
2. The Customer shall submit a standardised application for preliminary conditions for connection to info@ambergrid.lt
Submission of an application:
- Form of the application for connection;
- The Customer shall submit the other required documents together with the completed Form of the Application for Connection:
- Site plan showing the preferred connection point.
- Extract from the basic data of the Register of Legal Entities issued by the State Enterprise Centre of Registers (only for legal entities) or extract from the basic data of the Register of Legal Entities issued by another authorised body, if the applicant is a person registered outside Lithuania.
- Proof of representation (if applicable).
- Completed interested party verification questionaire form.
- Applications for the issuance of preliminary conditions for connection should be sent to info@ambergrid.lt
- If necessary, the TSO may request for clarification of the provided documents and data.
3. Amber Grid shall issue the preliminary conditions for connection
Issue of the preliminary conditions for connection:
- The TSO shall examine the application and issue the Customer with the preliminary conditions for connection no later than 30 calendar days from the date of submission of all required documents (if connection is available).
- The connection point shall be selected by the TSO, taking into account the location of existing or planned facilities or construction/installation as specified in the Customer’s application.
- The Customer can choose how the connection of the Customer’s biogas production facilities to the gas transmission system of the TSO shall be arranged, with the following 2 possible options:
- The works necessary for the connection of biogas production facilities on the gas transmission system operated by the TSO shall be carried out/organised by the TSO.
- The Customer shall design and/or construct/install and carry out works on behalf of the TSO on the gas transmission system (on its facilities or separate parts thereof) for the connection of biogas production facilities to the gas transmission system in accordance with the procedures and under the conditions set out in the gas system connection service agreement.
In all cases, the costs of the connection shall be covered by the Customer.
- The design and construction works for the part of the Customer’s biogas production facilities required for the connection shall in all cases be organised by the Customer.
- The provisions of the standard conditions for connection are set out (in Lithuanian).
Preliminary connection tariffs for works on the transmission system organised by the TSO
4. The Customer shall agree on the preliminary conditions for connection and submit an application for a connection service agreement
Agreeing on the preliminary conditions for connection and application for conclusion of a connection service contract:
- The preliminary conditions for connection issued by the TSO shall be valid for 12 months from the date of issue, and the connection service agreement must be concluded with the preliminary conditions for connection in force.
- Once the preliminary conditions for connection have been agreed and the Customer has fulfilled the preconditions (if any) set out therein, the Customer shall apply for conclusion of a connection service agreement and completed interested party verification questionaire form.
- The agreed preliminary conditions for connection shall be deemed to be the final conditions for connection and shall constitute an integral part of the connection service agreement.
The connection service agreement must be concluded during the period of validity of the preliminary conditions for connection, i.e. within 12 months from the issue thereof.
5. Amber Grid shall submit a draft connection service agreement, the agreement shall be signed
Drafting, negotiating and signing the connection service agreement:
- The TSO shall, within 60 calendar days from the receipt of the Customer’s request, prepare and submit to the Customer a draft connection service agreement, which shall include the final conditions for connection;
- Once the Customer and the TSO have agreed on the terms and conditions of the connection service agreement, the agreement shall be signed.
Below you will find guidance and information on what the Customer must do when:
- the Customer shall build the part of the transmission system necessary for the connection;
- the TSO shall build the part of the transmission system necessary for the connection.
6. The project manager shall be appointed and the contract shall be launched
|
When the Customer builds the part of the transmission system necessary for the connection |
When the TSO builds the part of the transmission system necessary for the connection |
|
|
7. Selecting suppliers/contractors
|
When the Customer builds the part of the transmission system necessary for the connection |
When the TSO builds the part of the transmission system necessary for the connection |
|
The Customer shall choose a qualified designer
Download the recommended Model Contract Work Agreement here (in Lithuanian). Amber Grid shall authorise the designer The developer shall be authorised by the TSO to represent the TSO in relations with third parties and carry out all actions and formalities on behalf of the TSO to the extent that the Law on Construction and other legislation regulating spatial planning, design and construction require the preparation of a construction design, its coordination, the organisation of the expert examination of the design, the supervision of the implementation of the design, and any other related actions, and the obtaining of construction permits on behalf of the TSO. The designer shall prepare the technical/working design and obtain the building permit
To submit the technical design and the technical working draft to the TSO for final approval only when they are complete, not as separate parts of the design.
The Customer shall choose a qualified contractor and equipment supplier
The TSO shall advise to proactively cooperate with suppliers to avoid shortages of materials and equipment, delays and non-compliance with delivery deadlines.
|
We recommend that you take into account that public procurement normally takes 6 months or more due to the legal requirements. For this reason, there are limited opportunities to negotiate favourable terms.
|
8. Construction works shall be carried out
|
When the Customer builds the part of the transmission system necessary for the connection |
When the TSO builds the part of the transmission system necessary for the connection |
|
|
9. Hot tapping and system interconnection works shall be carried out
|
When the Customer builds the part of the transmission system necessary for the connection |
When the TSO builds the part of the transmission system necessary for the connection |
|
|
10. Completion of construction, registration of new properties and settlement of accounts
|
When the Customer builds the part of the transmission system necessary for the connection |
When the TSO builds the part of the transmission system necessary for the connection |
- the National Energy Regulatory Council has issued certificates* for the technical inspection of the technical condition of the energy installations for both the Customer’s Site and the new part of the TSO system; - a Construction Completion Certificate** has been received; - debugging works on the commissioning of installed equipment have been carried out.
|
|
Upon connection of the biogas production facilities to the transmission system of Amber Grid, the following agreements shall be signed between the parties:
- Cooperation agreement, which shall set out the terms and conditions of cooperation between the TSO and the Customer. If you have any questions regarding the cooperation agreement, please contact us by e-mail pardavimai@ambergrid.lt or by telephone +370 699 07302.
- Gas transmission agreement (required before testing, trials of the biogas production plant system). Transportation of biomethane through the transmission system can be carried out either by the biomethane producer or by an authorised company with a gas transmission service agreement. For all the information you need on how to enter into a gas transmission service agreement, click here (in Lithuanian). For the gas transmission service agreement, please contact pardavimai@ambergrid.lt or call +370 699 07301.
- Guarantees of origin. Gas produced from renewable energy sources and supplied into natural gas networks may be covered by guarantees of origin. Guarantees of origin shall only be granted to market participants registered in the “Guarantee of Origin Register” administered by Amber Grid. For more information on how guarantees of origin are granted and the fees for services, please look Guarantees of Origin for Green Gas.